Experience – Water Treatment Facilities
Bethel Park Sewage Treatment Plant Piney Fork Plant




LOCATION:
Bethel Park, PA
OWNER:
Bethel Park Municipal Authority
OWNER’S REP:
Superintendent
3100 Piney Fork Road
South Park, PA 1512
PROFESSIONAL:
HDR Engineers, Inc.
3 Gateway Center
Pittsburgh, PA 15222
PROJECT DESCRIPTION:
09-01-2006 Mobilization
09-30-2008 Completion
Completed on schedule
CONTRACT VALUE:
Final Contract: $6,295,000.00
WCI PROJECT MANAGER:
Joseph Pace
WCI PROJECT FOREMAN:
Fred Frueh, Local #449
WCI PROJECT SUPPORT:
Project Estimator: Dan Paulovich
Project Procurement: Dan Paulovich
PROJECT RECAP:
Construction of two trickling filter basins and new pump station complete with concrete, mechanical and plumbing piping and HVAC systems.